Surge tank level

A buffer vessel between two plant sections. Its job is to keep the outflow smooth by using its own volume. Tight level control is the wrong answer here; a loosely tuned P or PI is the right one.

Plant Dynamics at Nominal Point

FOPDT dynamics & controllability regime
Open on the bench🧩 Build in Block Studio
Dead time θ4.5 snothing happens for this long after the valve moves
Time constant τ—no settling: it ramps
Ramp rate k′−0.00139 /s% of span per second, per % of valve
Integrating (1/s) — Needs careful reset TiIntegrating process (no self-regulation)
0% Pure lag (fast PI)50% Balanced100% Pure delay (needs Smith / MPC)
Linearized model at 1.5 m:
G(s)≈−0.00139 e−4.5ssG(s) \approx \frac{-0.00139\,e^{-4.5s}}{s}
Verdict: PID is the answer

A slow P or PI, tuned from the room the tank has. The scorecard's IAE will call it terrible, and that's the wrong measure here: the outflow moves about eight times more gently than with a tight tuning, and the downstream section never sees the upstream swings. Protect the limits with an override or a trip, not by tightening the loop. With the override there the PI can run looser still: about three times calmer through normal surges, at the price of a sharp move when the override takes over on a big one.