Belt feeder (dead time)

A screw feeder drops material onto a conveyor, and a weigh belt measures the rate 30 s later. The dead time dwarfs everything else: plain feedback can only be slow, unless the controller predicts what the scale is about to see.

Plant Dynamics at Nominal Point

FOPDT dynamics & controllability regime
Open on the bench🧩 Build in Block Studio
Dead time θ32.8 snothing happens for this long after the valve moves
Time constant τ5.5 sthen 63 % of the way in this long
Gain K0.8% of span the PV moves per % of valve
Dead-time dominant (θ/τ ≥ 1) — Hard: needs Smith/MPCDelay share: 85.6% (θ/τ = 6)
0% Pure lag (fast PI)50% Balanced100% Pure delay (needs Smith / MPC)
Linearized model at 10 t/h:
G(s)≈0.8 e−32.8s5.5s+1G(s) \approx \frac{0.8\,e^{-32.8s}}{5.5s + 1}
Verdict: PID falls short

A PI tuned with τc≈θ\tau_c \approx \theta is the honest baseline. A Smith predictor roughly halves the IAE, mostly on setpoint changes: it settles in about 55 s instead of 90 s. It does little for density upsets, which nothing can see until they reach the scale. State feedback whose observer carries the belt's dead time and estimates the upset does better again: a third of the Smith predictor's setpoint error, a quarter of its screw travel and better margins (Ms 1.8 against 2.0), though it recovers from density upsets more slowly (about 128 s against 94).

It is worth it when rate changes are frequent and the dead time is known and stable. Tie the model's dead time to the belt speed if the belt can change speed. Tune the PI inside the predictor no faster than about half the dead time, or a slowed belt will make it ring.