Crane with a swinging load

An overhead crane trolley moving a load hanging on an 8 m rope. Every acceleration sets the load swinging with a 5.7 s period and almost no damping. Getting the load to where it should be, without sway, is a job for state feedback.

Plant Dynamics at Nominal Point

FOPDT dynamics & controllability regime
Open on the bench🧩 Build in Block Studio
Dead time θ2.28 snothing happens for this long after the valve moves
Time constant τ—no settling: it ramps
Ramp rate k′0.05 /s% of span per second, per % of valve
Integrating (1/s) — Needs careful reset TiIntegrating process (no self-regulation)
0% Pure lag (fast PI)50% Balanced100% Pure delay (needs Smith / MPC)
Linearized model at 20 m:
G(s)≈0.05 e−2.28ssG(s) \approx \frac{0.05\,e^{-2.28s}}{s}
Verdict: PID falls short

State feedback with a sway measurement and an observer that knows about the wind. It carries the load 20 m in 23 s and puts it down hanging still (0.09° of swing left), rejects a 4 kN gust within 8 s, and still works with the load 5 m lower than designed for.

The best PI on the load position takes over a minute for the same move and leaves 2° of swing. This is one of the places on the ladder where PID simply can't do the job, because it has nothing with which to damp the swing.

Loading the comparison…